Case Study: DUBAI TERMINAL 3, DUBAI AIRPORT
November 13, 2008
 |
Project: Terminal 3, Dubai Airport,
Dubai, U.A.E.
Owner: Dubai Civil Aviation (DCA)
& Dubai Municipality
Architect: Aeroports De Paris
International (ADPI) (Dubai) & Dar Al Handasah Consultants (Shair &
Partners) (Dubai)
General Contractor: Al Habtoor
Engineering-Murray & Roberts JV (HMR) (Al Habtoor Group) (Dubai)
Stone Contractor: Dar Al Rokham LLC
Stone Supplier: Campolonghi, Henraux,
Technostone
Sealer Distributor: IKAN, Inc.
Sealer Manufacturer: Custom
Building Products |
|
Six-Sided Sealing from Aqua
Mix Preserves Beauty of Stone in Dubai’s New Terminal
Dubai
International Airport is one of the world’s fastest-growing airports, and is in
the midst of a long-term plan for expansion. Terminal 3 was recently completed
after three years of construction, and features 3.8 million square feet of a
Brazilian stone called Panha Fragola Corcovado, or “PF”. PF presented a serious
sealing challenge because the stone contains soluble pyrite (an iron sulphide)
which can absorb water from the mortar bed during curing and cause severe
discoloration. IKAN, Inc, a local distributor of Aqua Mix care and maintenance
products, recommended a six-sided sealing solution in order to protect the
stone from moisture throughout the 28-day curing process.
Extensive testing was conducted by Aqua Mix technical experts,
with two new products that were not even on the market yet, UltraSolv® and
EconoSeal™. First, local materials were used in order to duplicate the
installation conditions, while confirming with control groups that the
discoloration from soluble pyrite would in fact occur without proper sealing.
Next, IKAN performed submersion and mortar bed tests with PF stone sealed on
all six sides with EconoSeal and UltraSolv. Both sealers performed
impressively, keeping water at bay for the required 28 days and preventing
discoloration. Finally, tests were done to prove that neither sealer would
compromise shear bond strength.
After successful testing, EconoSeal was selected for the
initial six-sided sealing, with UltraSolv specified for final sealing of the
installed surface. Stone was laid out, sealed on six sides with Econoseal, and
cured for 24 hours prior to installation. UltraSolv was applied to the finished
surface just prior to completion of the entire terminal. During this period
both UltraSolv and EconoSeal products were launched for sale internationally.
IKAN assisted the
primary stone contractor, Al Habtoor, throughout the 2-year process, providing
onsite support, quality control and education for the ever-changing staff of
over 400 tradesmen imported from other countries to work on the project. The
result is a stunning, pristine installation that has no trace of soluble pyrite
or any other staining. In fact, the sealing project was so successful that Aqua
Mix sealers, from Custom Building Products, will be used on the next new
terminal at Dubai International Airport, already underway. - Monica Catalani, Product
Manager
|